The PCB lamination process is one of the key processes in the manufacture of multilayer circuit boards. The lamination processing of multi-layer circuit boards is to laminate layer by layer through pre-stacking and laminating machines, and then to heat, pressurize and vacuum in the hot press of PCB laminating machine, and press according to the set pressing program. After pressing, the single and double layer inner circuit core boards are combined into multiple and high-rise circuit boards. PCB laminating machine and laminating machine is the key equipment of PCB laminating process, must give priority to ensure their stable operation. The problem of abnormal lifting of the stacking table seems simple, but it is not easy to find the reason.

First of all, check and confirm whether the photoelectric switch of the working position of the rising row board is abnormal. These old devices have no I/O point display on the touch screen, which is inconvenient to check and basically needs to be disassembled for inspection.

Secondly, check the B, C, D, E four travel switch. B is the forward deceleration position of the chassis, C is the forward positioning of the chassis, D is the discharge position of the chassis, and E is the positioning under the working of the chassis plate. Make sure that each sensor and cylinder clamping magnetic switch are in place and well sensed.

Finally, to check the hydraulic lifting platform lifting telescopic cable, whether there is damage. This is more difficult to find. It is good and bad. When the chassis comes in, it is normal. When the clamping cylinder moves and vibrates, it breaks down. At this time, take off the lid, shake the thread and move it. It is 90% the thread problem.

Peel the suspicious cable and pull it. If it breaks, you can find the line breakpoint. Reconnect the line, arrange the line, and you can run it.
Previous Page
Previous Page
More news
Jiangsu Shengyi High Frequency Communication Substrate Project Foundation Laying Ceremony Held
2024/03/01
2024/03/01
Jiangxi Jiujiang PCB Project Formed a Complete Industrial Chain
2024/03/01
Service Hotline
8615989495260
Add: No.21,6/F. FuHong Bldg.No.120 Yongfu road,Qiaotou community, Fuhai street, Baoan district,Shenzhen P.R. China
Telephone: 86 - 755 - 26400459
Fax: 86 - 755 - 26487289
Mobile phone: Mr. Li 86 - 15989495260
Email:limiao@szvstar.com ericzhao@szvstar.com
Mobile website
Focus on us
Copyright©2023 All rights reserved of Shenzhen V-STAR Industry & Trade Co.,LTD.